The Precast Concrete Homes’ 8 Week Building Process

How do we help you build a better, stronger home faster than any other method?

Simple.

By getting you to lockup in 10 days instead of 8 weeks.

By reducing the amount of trades you need to coordinate.

By providing you with a system that allows more trades to work concurrently on the same home.

The process is not that different to how a home is currently built. It is just more efficient.

Days 1 and 2concrete-building-process

Pour pads for walls to stand on.
Install precast walls.

Days 3 and 4

Install roof trusses.

Day 5

Pour slab.

Days 6 – 10

Install Roof and Guttering
Install doors, windows and eaves.
Complete plumbing and electrical rough in.
Install insulation and ducting.
House is now locked up and ready to be sheeted.

Days 11 – 40

Sheet interior walls and waterproof wet areas.
Complete tiling and install kitchen and bathroom fittings.
Complete fixout and painting.
Complete externals including; painting, paths, driveway and landscaping.

End of week 8 – House complete.